This glossary defines the terms mechanical engineers and contractors use in commercial HVAC load, ventilation, and air distribution design, from Radiant Time Series and block loads to Vbz, Ez, and external static pressure. Each definition is short enough to quote, names the standard it comes from, and links to how HVAKR calculates it. Formulas use I-P units and standard air unless noted.
Loads and calculation methods
- Heat gain
The rate at which heat enters or is generated in a space at a given moment, through the envelope, from the sun, or from people, lights, and equipment. Only the convective part becomes cooling load right away; the radiant part is absorbed by surfaces and released later.
- Cooling load
The rate at which heat must be removed from a space to hold its indoor design temperature and humidity, in Btu/h or tons. It lags and smooths the heat gain because building mass stores radiant heat.
- Heating load
The rate at which heat must be added to hold the indoor heating setpoint at the winter design condition. It's usually calculated steady-state and conservatively; HVAKR takes no solar credit.
- Sensible load
The part of a load that changes the air's dry-bulb temperature, from conduction, solar gain, lights, equipment, and the dry part of people and outdoor air loads.
- Latent load
The part of a load tied to moisture added to or removed from the air. It changes humidity ratio, not temperature, and comes mainly from people, outdoor air, infiltration, and wet processes.
- Sensible heat ratio (SHR)
Sensible load divided by total load (sensible plus latent). A low SHR means the coil must remove more moisture per unit of cooling, which drives coil selection and dehumidification strategy.
- Peak load (design load)
The highest load found across the design conditions checked. HVAKR calculates a 24-hour profile for every month, 288 month-hour points, and reports the peak month and hour for each space, zone, and system.
- Block load
The load of a whole zone, system, or building calculated at its own single peak hour. It's used to size central equipment and is smaller than the sum of space peaks because spaces peak at different times.
- Sum of peaks (noncoincident load)
The total of each space's individual peak regardless of when it happens. It's used to size airflow to each space and terminal unit, while the block load sizes the central unit.
- Diversity
An allowance for loads or occupants that don't all occur at once. In ASHRAE 62.1 the occupant diversity ratio D reduces the people part of system outdoor air.
- Radiant Time Series method (RTS)
ASHRAE's simplified design cooling load method, derived from the heat balance method. It splits each heat gain into radiant and convective parts, delays conduction through walls and roofs with conduction time series, and converts radiant gains into cooling load over the next 24 hours with radiant time series. HVAKR and Revit's built-in Heating and Cooling Loads tool both use RTS.
- Heat Balance method (HB)
ASHRAE's reference load method, which solves a heat balance at every inside and outside surface and the zone air at each time step. EnergyPlus is a heat balance engine, and Carrier HAP and Trane TRACE 3D Plus describe heat balance methods.
- CLTD/CLF method
An older ASHRAE cooling load method using tabulated cooling load temperature differences, cooling load factors, and solar cooling loads. The Handbook replaced it with RTS, but some tools still offer it for hand-check comparisons.
- Sol-air temperature
The outdoor temperature that, with no sun, would drive the same heat into an outside surface as the real mix of solar radiation, outdoor air temperature, and sky radiation. RTS uses it for wall, roof, and door conduction.
- Conduction time series (CTS)
A set of 24 coefficients that spreads a wall's or roof's conduction heat gain over the following hours, so heavy constructions peak later. HVAKR takes it from the ASHRAE wall type.
- Internal gains
Heat from people, lighting, equipment, and miscellaneous sources inside the space, each following a usage schedule. In HVAKR they come from the space type and its schedules.
- Infiltration
Uncontrolled outdoor air leaking in through cracks, openings, and doors, as opposed to ventilation air delivered on purpose. HVAKR reports general, window, and door infiltration as separate streams.
- Air changes per hour (ACH)
Airflow expressed as how many times per hour it would replace the room's volume: ACH = cfm × 60 ÷ room volume in ft³. Used for infiltration rates and for minimum airflow in some space types.
Standards and manuals
- ANSI/ASHRAE/ACCA Standard 183
"Peak Cooling and Heating Load Calculations in Buildings Except Low-Rise Residential Buildings." It sets minimum requirements for how a commercial load calculation is done and documented, rather than prescribing one method.
- ASHRAE Standard 62.1
"Ventilation and Acceptable Indoor Air Quality," the standard for minimum outdoor air and related requirements in buildings other than residential dwelling units. In HVAKR the edition (2025 or 2022) is a project setting; both use the 62.1-2022 rate library, and the 2025 setting adds an air density correction.
- ASHRAE Standard 62.2
The ventilation standard for residential dwelling units.
- ASHRAE Standard 170
"Ventilation of Health Care Facilities," which sets air change rates, outdoor air, pressure relationships, and design conditions for the healthcare spaces it covers. HVAKR includes ASHRAE 170 space-type templates.
- ASHRAE Standard 90.1
The energy standard for buildings except low-rise residential, covering envelope, HVAC, lighting, and power requirements. HVAKR can start a project's envelope from ASHRAE 90.1-2022 minimums.
- ACCA Manual J
ACCA's residential load calculation procedure, now in its 8th Edition. Many building departments ask for Manual J calculations from software on ACCA's approved list for residential permits. HVAKR doesn't do residential Manual J.
- ACCA Manual N
ACCA's commercial load calculation procedure, now in its 5th Edition.
- ACCA Manual D and Manual S
ACCA's residential duct design procedure (D) and residential equipment selection procedure (S), used with Manual J.
Design conditions and weather
- Design conditions
The outdoor temperatures and humidity a system is sized for, taken from climatic design data for the nearest weather station at a chosen percentile. HVAKR supports ASHRAE (2025, 2021) and CIBSE (2015) data.
- 0.4% cooling design dry-bulb
The dry-bulb temperature exceeded during only 0.4% of the hours in the period, about 35 hours a year on the annual basis. HVAKR uses ASHRAE's monthly 0.4% values by default, with 2%, 5%, and 10% available.
- Mean coincident wet-bulb (MCWB)
The average wet-bulb temperature that occurs at the design dry-bulb. It sets the outdoor air's moisture for the cooling load.
- 99.6% heating design dry-bulb
The dry-bulb temperature that outdoor air falls below during only 0.4% of the year's hours. HVAKR uses 99.6% by default, with 99% available.
- Design day
A 24-hour profile of outdoor dry-bulb, wet-bulb, and solar conditions for a month, built from the design values. RTS runs the loads hour by hour across it.
- Climate zone
The ASHRAE/IECC classification of a location by temperature (zones 0 to 8) and moisture (A humid, B dry, C marine). It sets envelope and equipment requirements in energy codes. HVAKR shows the climate zone of the project's selected weather station.
Envelope
- U-factor
The overall heat transfer coefficient of an assembly, in Btu/(h·ft²·°F). Lower is better insulated. For layers in series it's the inverse of the total R-value, including air films.
- R-value
Thermal resistance, in h·ft²·°F/Btu. Layer R-values add in series; the assembly's U-factor is 1 divided by the sum.
- Solar heat gain coefficient (SHGC)
The fraction of incident solar radiation that gets through a window as heat, both transmitted directly and absorbed then released inward. It runs from 0 to 1; lower means less solar gain.
- Surface absorptance
The fraction of incident solar radiation an opaque surface absorbs. It sets how hot a wall or roof gets in the sun; in HVAKR it comes from the wall or roof type's absorptance, not its display color.
- F-factor
The heat loss coefficient of a slab-on-grade floor per linear foot of exposed perimeter, in Btu/(h·ft·°F). Slab losses are calculated from perimeter, not area.
- Fenestration
All glazed openings in the envelope: windows, skylights, and glazed doors. It usually drives perimeter cooling loads through solar gain.
Ventilation (ASHRAE 62.1)
- Ventilation Rate Procedure (VRP)
The prescriptive ASHRAE 62.1 procedure that sets minimum outdoor air from per-person and per-area rates for each occupancy category, then corrects for air distribution and system type.
- Indoor Air Quality Procedure (IAQP)
The performance-based ASHRAE 62.1 procedure that sets outdoor air from target concentrations of design compounds and can credit air cleaning. HVAKR can calculate IAQP outdoor air per space and falls back to VRP when it can't.
- Rp (people outdoor air rate)
Outdoor airflow required per person for an occupancy category, in cfm per person, from the 62.1 rate table.
- Ra (area outdoor air rate)
Outdoor airflow required per square foot of floor area for an occupancy category, in cfm/ft², from the 62.1 rate table.
- Pz (zone population)
The largest number of people expected in the ventilation zone during typical use.
- Az (zone floor area)
The net occupiable floor area of the ventilation zone, in ft².
- Vbz (breathing zone outdoor airflow)
The outdoor air the occupied breathing zone needs: Vbz = Rp × Pz + Ra × Az.
- Ez (zone air distribution effectiveness)
How well the supply air delivers outdoor air to the breathing zone. Ceiling supply of cool air is 1.0; ceiling supply of warm air 15°F or more above space temperature with ceiling return is 0.8. In HVAKR you set Ez on the space type (default 0.8).
- Voz (zone outdoor airflow)
The outdoor air that must be supplied to the zone after the distribution correction: Voz = Vbz ÷ Ez.
- Occupant diversity (D)
The ratio of the system's actual population to the sum of the zone populations it serves, D = Ps ÷ ΣPz. It applies to the people part of a multiple-zone system's outdoor air.
- Vou (uncorrected outdoor air intake)
A multiple-zone system's outdoor air before the efficiency correction: Vou = D × Σ(Rp × Pz) + Σ(Ra × Az).
- System ventilation efficiency (Ev)
How well a multiple-zone recirculating system gets outdoor air to its most critical zone. ASHRAE 62.1 gives a simplified value and a detailed Appendix A procedure; HVAKR uses the simplified value (0.75, or 0.88 × D + 0.22 when D is below 0.60).
- Vot (outdoor air intake flow)
The outdoor air the air handler must bring in: Voz for a single-zone system, ΣVoz for a 100% outdoor air system, and Vou ÷ Ev for a multiple-zone recirculating system.
- Dedicated outdoor air system (DOAS)
A unit that conditions and delivers 100% outdoor air separately from the equipment that handles space heating and cooling. HVAKR labels its outdoor air as Direct when a DOAS serves the space.
- Exhaust air
Air removed from a space and discharged outdoors, such as toilet, kitchen, or lab exhaust. Exhaust requirements are separate from the outdoor air minimum.
- Transfer air
Air moved from one space to another, often to make up exhaust in toilets or janitor closets. HVAKR keeps it as separate design data and never subtracts it from required exhaust.
Airflow, equipment, and ducts
- Supply airflow (cfm)
The air delivered to a space to meet its sensible load: cfm = sensible load ÷ (1.08 × ΔT), with load in Btu/h and ΔT the room-to-supply temperature difference in °F, for standard air.
- Ton of refrigeration
A unit of cooling capacity equal to 12,000 Btu/h.
- Air handling unit and rooftop unit (AHU, RTU)
Central equipment that moves and conditions air with fans, coils, filters, and dampers; an RTU is a packaged unit on the roof. HVAKR calls these central units.
- Variable air volume (VAV)
A system that holds supply air temperature roughly constant and varies airflow to each zone with terminal boxes to match load.
- Terminal unit
The zone-level device between the central system and the space: a VAV box, fan-powered box, fan coil, or similar.
- External static pressure (ESP)
The pressure, in inches of water column, that a unit's fan must overcome outside the unit: ductwork, fittings, terminals, grilles, and any field-installed accessories.
- Friction rate
Pressure loss per 100 ft of straight duct, in in. w.c. per 100 ft. HVAKR sizes each duct against a max pressure drop and max velocity set on its duct type.
- Velocity pressure
The kinetic pressure of moving air. For standard air, VP = (V ÷ 4,005)², with V in fpm and VP in in. w.c.
- Fitting loss coefficient (C)
A dimensionless factor that, multiplied by velocity pressure, gives the pressure loss through a fitting such as an elbow or wye. HVAKR applies project-wide coefficients per fitting type.
- Equal friction method
A duct sizing method that sizes every section for the same friction rate. Simple and common for low-pressure supply and return.
- Static regain method
A duct sizing method that sizes each section so the pressure regained as air slows after a branch offsets the friction loss to the next branch, keeping static pressure near constant at each takeoff.
- Noise criteria (NC)
A single-number rating of background sound against NC curves, used to select diffusers and registers for a room's acceptable noise. HVAKR's register schedule reports the NC each register runs at.
- Air balance (pressurization)
The net of supply, transfer in, return, exhaust, and transfer out for a space. Positive pressurizes the space; negative keeps air from leaving labs, toilets, and kitchens.
- Psychrometrics
The properties of moist air (dry-bulb, wet-bulb, dew point, humidity ratio, enthalpy) and how they change through coils and mixing.
Project and workflow terms
- Basis of design (BOD)
The document and settings that record a project's design criteria: codes and standards, weather data, indoor conditions, envelope types, space types, and system types. In HVAKR it's a project section that every calculation reads from.
- Space
The smallest unit of a load calculation: a room or area with its own boundaries, envelope, space type, and loads.
- Zone (thermal zone)
One or more spaces controlled together by one thermostat or terminal unit.
- System
The equipment that serves a set of zones, such as one AHU with its terminal units. Block loads and system outdoor air are calculated at this level.
- Space type
A reusable set of design inputs for a kind of space: occupancy, 62.1 rates, Ez, lighting and equipment loads, schedules, and indoor setpoints.
- Takeoff
Measuring spaces, areas, and envelope from drawings to build the load model. HVAKR AI proposes spaces from uploaded floor plans and the engineer approves them.
- gbXML
Green Building XML, an open schema for passing building geometry, constructions, and spaces between BIM tools such as Revit and analysis tools. HVAKR exports a gbXML model on Team plans and up; it carries geometry, constructions, and inputs, not calculated loads.
Frequently asked questions
What is the difference between heat gain and cooling load?
Heat gain is the rate heat enters or is generated in a space at a given moment. Cooling load is the rate the system must remove heat to hold the setpoint. They differ because the radiant part of heat gain is absorbed by walls, floors, and furniture and released later, so the cooling load lags and flattens the heat gain.
What is the difference between Vbz and Voz in ASHRAE 62.1?
Vbz is the outdoor air the breathing zone needs, Rp × Pz + Ra × Az. Voz is the outdoor air you must supply to the zone to deliver that, Vbz ÷ Ez, which is larger whenever the air distribution is less than fully effective.
What is the difference between a block load and the sum of peaks?
A block load is the load of a whole zone, system, or building at its single peak hour, used to size central equipment. The sum of peaks adds each space's own peak regardless of hour and is used to size airflow to each space, so it's always equal to or larger than the block load.
Which load method does ASHRAE recommend for commercial buildings?
The ASHRAE Handbook of Fundamentals presents the heat balance method as the reference and the Radiant Time Series method as its simplified procedure for design cooling loads. ANSI/ASHRAE/ACCA Standard 183 sets minimum requirements for peak load calculations, and how they're documented, in buildings other than low-rise residential.
Sources
- HVAKR docs: load calculations Checked
- HVAKR docs: cooling Checked
- HVAKR docs: heating Checked
- HVAKR docs: ventilation Checked
- HVAKR docs: ASHRAE 62.1 Checked
- HVAKR docs: ASHRAE 183 Checked
- HVAKR docs: weather Checked
- HVAKR docs: space types Checked
- HVAKR docs: system types Checked
- HVAKR docs: air balancing Checked
- HVAKR docs: duct layout Checked
- HVAKR docs: PDF export Checked
- HVAKR ASHRAE 183 compliance page Checked
- ACCA Manual N (5th Edition) Checked
- ACCA approved software Checked
- Autodesk Help, Revit Heating and Cooling Reference (RTS) Checked